Appendix SiUS39-506
124 General Information
Before turning on the power
Inspection item
Inspection method
Standard (guideline) Measurement values
Decision
Breaker capacity Visual inspection Specified capacity G NG
Refrigerant piping system
Gas detector No leaks G NG
Heat exchanger Visual inspection
No clogging or damage
G NG
Terminal connection section
Screwdriver, etc. No looseness G NG
Fan motor electrical insulation
500-V electrical insulation tester
1 M or more M
Compressor electrical insulation
500-V electrical insulation tester
1 M or more
Installation Visual inspection Short circuit, etc. G NG
Refrigerant piping system
Gas detector No leaks G NG
Heat exchanger Visual inspection
No clogging or damage
G NG
Terminal connection section
Screwdriver, etc. No looseness G NG
Fan motor electrical insulation
500-V electrical insulation tester
1 M or more M
Compressor electrical insulation
500-V electrical insulation tester
1 M or more
Installation Visual inspection Short circuit, etc. G NG
System name
Outdoor unit 1
INV M
STD1 M
STD2 M
Outdoor unit 2