www.DaikinApplied.com 19 IOM 1210-1 • MAGNITUDE
®
MODEL WMC CHILLERS
InsTallaTIon
Pre-Start Checklist
©2014 Daikin Applied Form SF-111
MAY 2014
Pre-Start ChecklistCentrifugal Chillers
Must be completed, signed and provided to Daikin Applied Service Dept. at least 2 weeks prior to requested start date.
Job Name
Installation Location
Customer Order Number
Model Number(s)
E.O./G.O. Number(s)
Chilled Water
Yes
No
N/A
Initials
Piping Complete
Water System- flushed, filled, and vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls operational (3-way valves, face/bypass dampers, bypass valves, etc.)
Water system operated and tested; flow meets unit design requirements
Condenser Water
Yes
No
N/A
Initials
Cooling tower flushed, filled, and vented; Water treatment in place
Pumps installed and operational (rotation checked, strainers installed and cleaned)
Controls (3-way valves, bypass valves, etc.) operable per IM or IOM
Water system operated and flow balance to meet unit design requirements
Electrical
Yes
No
N/A
Initials
*115 volt service completed, but not connected to control panel (when applicable)
Line Power leads(a) connected to starter; *Load leads(b) run from starter to compressor and ready
for connection by Service (Do not connect load leads to starter or compressor terminals) See Notes 1, 4
All interlock wiring complete and compliant with Daikin specifications
Starter complies with Daikin specifications
*Oil cooler solenoid wired to control panel as shown on wiring diagram (See Notes)
Pump starters and interlocks wired
Cooling tower fans and controls wired
Wiring complies with National Electrical Code and local codes (See Note 4)
Condenser pump starting relay (CP1,2) installed and wired (See Note 3)
Miscellaneous
Yes
No
N/A
Initials
*Oil cooled water piping complete. (Units with water cooled oil coolers only)
Relief valve piping complete (per local codes
Thermometers, wells, gauges, control, etc., installed
Minimum system load of 80% capacity available for testing/adjusting controls
Document Attached: Technical Breakdown from DaikinTools
Document Attached: Final Order Acknowledgement
Notes: The most common problems delaying start-up and affecting unit reliability are:
1. Field installed compressor motor power supply leads too small. Questions: Contact the local Daikin Applied sales rep* State size, number and
type of conductors and conduits installed:
a. From Line Power supply to starter
b. From starter to chiller unit (remote mounted)
2.
Centrifugal chillers with water-cooled oil coolers must have a 115-volt normally-closed water solenoid valve installed in the oil cooler water supply
line. Daikin recommends ASCO Type 8210B27 solenoid valve or approved equal and 40-mesh strainer. Daikin does not supply these components.
3. A 115 volt field supplied relay (CP1,2) must be used to start and stop condenser water pump on most applications. Cold condenser water must not
flow through condenser during compressor off cycle. Provisions have been made in control center for connecting CP relay, but must not have a rating
in excess of 100 VA.
4 Refer to NEC Article 430-22 (a)
Contractor Representative
Daikin Applied Sales Representative
Signed:
Signed:
Name:
Name:
Company:
Company:
Date:
Date:
Phone/Email:
Phone/Email:
* Does Not Apply to Magnetic Bearing Chillers (WMC/WME)